There are 3 types of BITE (Built-In Test Equipment):
- power up
- interruptive
- continues
which one of these is being used after installation of a new display on an aircraft?
There are 3 types of BITE (Built-In Test Equipment):
which one of these is being used after installation of a new display on an aircraft?
First, let's clarify the terms.
BITE (Built-In Test Equipment) is the hardware and software within a product that performs BIT (Built-In Test).
There are three common forms of BIT:
So to your question; when a new display is installed (or any other unit is replaced) and power is restored the unit will perform a PBIT and potentially begin CBIT (if it exists). After the unit is in normal operation, the technician that replaced it will normally perform an IBIT and verify the unit passed all tests.
It's important to remember that BIT is intended to identify hardware faults. If you are concerned with 'glitches' due to flipped bits (caused by single event upsets) or similar, that is typically addressed using integrity monitoring. This is more common than CBIT and it will only flag 'bad data' as it can't specifically identify what caused a fault. It only identifies that data is suspect as the primary computation and the monitor disagree. A hardware failure will generally result in the integrity monitor providing a continuous fault condition, but it's primary purpose is to identify 'soft' or intermittent faults.
All three of these types of test will likely be conducted when a new display is installed in to an aircraft and they would happen each time the aircraft is powered on.
The only difference between a new installation and an existing installation is that the BITE might raise a problem with the software loaded. If an aircraft has three displays and one of them is replaced with a new one, it might have a different version of software loaded on to it. The BITE might contain a compatibility check to ensure that all the displays are running the same version of software.